Looking for a Contractor?
Looking for a Contractor?

Alchatek Blog

Case Study - Bridge Approach Slab Leveling

Posted by Kreg Thornley on Oct 16, 2024 10:00:00 AM

Banner Bridge Approach Slab Leveling

Body Bridge Approach Slab LevelingA critical infrastructure issue emerged on a four-lane road near downtown San Francisco. Soil erosion caused a bridge approach slab to settle 2.5 to 3 inches over time. The affected area had an asphalt surface with a thin sleeper slab underneath. California Department of Transportation (Caltrans) engineers initially advocated for complete replacement. The situation changed when Bay Area Underpinning entered the scene. Together with Alchatek, they presented an alternative solution: Deep Lock® soil stabilization and concrete leveling. After careful consideration, the DOT engineers agreed to try this innovative approach. This method promised to minimize traffic disruption and significantly reduce costs compared to full replacement, which would have required closing the entire roadway and replacing a 40x12 foot area of asphalt and sleeper slab.

Powerful Polymers

The project team chose AP Lift 475 as the repair material. This substance offers impressive compressive strength while maintaining good expansion properties. Once injected, the material spreads out effectively, filling voids in the annular space within the soil. This combination of strength and expansion makes AP Lift 475 ideal for stabilizing and leveling the settled bridge approach slab. The material's ability to penetrate and fill voids addresses the underlying cause of the settlement, providing a more comprehensive solution than - for example - simply adding a new surface layer.

Painless Procedures

Before starting the repair, DOT engineers conducted thorough soil testing. They performed soil borings to determine soil types and characteristics at various depths. This crucial step provided insights into the subsurface conditions contributing to the settlement. Additionally, they used a DCP (Dynamic Cone Penetrometer) test to identify areas of weak soil density. Armed with this information, the contractor developed an optimal application plan.

The team installed injection tubes on four-foot centers at six- and 10-foot depths. They injected about 40 pounds of material per tube, using 10-15-second shots. This measured approach allowed for controlled material distribution. Throughout the process, the team carefully monitored the slab lift using a rotary laser and zip-level altimeter. These precise instruments ensured even raising of the slab to the desired level, preventing any potential issues from uneven lifting.

Rapid Results

The modular approach to repair minimized traffic disruption, a critical factor for this busy thoroughfare. At any given time, only two out of four lanes remained closed. Consequently, traffic continued to flow throughout the project, preventing gridlock in the area. The team completed the entire leveling process in just four eight-hour shifts, a remarkably short timeframe for such a significant repair. Compared to full replacement, the method significantly cut labor requirements, traffic disruption, and financial costs. Moreover, the repair addressed the root cause of the problem by stabilizing the eroded soil beneath the roadway.

Unlike simply adding an asphalt layer for leveling, which would have provided only a temporary fix, this solution offers long-lasting results. By directly treating the underlying issue, the team greatly reduced the likelihood of recurrence. The success of this project offers a blueprint for similar infrastructure challenges. It showcases how modern materials and techniques can provide cost-effective, efficient, and durable solutions to complex engineering problems. 

Want more information on Deep Lock® soil stabilization and slab lifting?

Download an Info-Packed Slab Lift Brochure!

Download an Info-Packed Deep Lock Brochure!

Topics: All Posts, Lift Slabs, Stabilize Soil, Deep Lock

Spots Filling Quickly - Alchatek 2024 Fall Geotech Training

Posted by Kreg Thornley on Oct 7, 2024 10:00:00 AM

Banner - 2024 Fall Geotech Training

Body - 2024 Fall Geotech Training-2Essential Details

Dates/Pricing

Geotechnical Masterclass: November 12th-14th, 2024 – $745.00

Location

Atlanta, GA

Discount

$50 discount for each additional participant.

Click Here to Register NOW!

Geotechnical Masterclass

Elevate your geotechnical expertise with our comprehensive masterclass covering cutting-edge techniques and solutions. Master:

  • Polyurethane Concrete Leveling for sunken slabs
  • Polyurethane Soil Stabilization for various soil types
  • Geotechnical Testing with precision
  • Deep Lock® soil stabilization procedures

Why Attend?

Gain Hands-On Experience with state-of-the-art equipment
Learn From Industry-Leading Experts with decades of experience
Network with Peers and potential collaborators
Boost Your Company’s Market Reach and capabilities

Consider the low cost of training vs. the high cost of job screw-ups and missed opportunities.

Transitioning from routine geotechnical work to more complex and high-stakes infrastructure and large-scale construction projects represents a significant growth opportunity for your career and business. Get the advanced skills and critical insights needed to tackle challenging projects and succeed in competitive markets confidently.

Join us for this transformative Geotechnical Masterclass. We’ll equip you with the knowledge and techniques to excel across all geotechnical project types.

Click Here to Register NOW!

Topics: All Posts, Lift Slabs, Stabilize Soil, Business Tips, Fill Voids, Deep Lock, Training, Municipal Resources, Events

Case Study - Parking Lot Stabilization

Posted by Kreg Thornley on Oct 2, 2024 10:00:00 AM

Banner - Parking Lot Stabilization

Body - Parking Lot StabilizationAtlanta geotech contractors Lift It Rite were contacted by Deas Construction regarding the settlement of parking lot pavement behind the loading docks at a manufacturing plant in Norcross, GA.  The following observations were made during this first visit:

  • An area of concrete slab pavement, approximately 75’ x 25’, surrounding a crane and a steel rack showed signs of settlement. 
  • Holes drilled in random spots within the 75’ x 25’ area revealed voids up to 24” directly beneath the slab.
  • Manual probing of the soil indicated it was quite soft.

Calculations were made for filling the voids and lifting the slab using high-density polyurethane, the DOT's product for highway stabilization and bridge approach slab leveling.  However, it was agreed that further investigation into this settlement's cause was warranted before proposing the void fill and lift.  Ground Consolidation Services of Tucker, GA, was asked to come in and do some GPR (ground-penetrating radar) readings and DCP (dynamic cone penetrometer) testing to determine the compaction of the soil.  Results indicated the following:

  • Confirmation of voids beneath the concrete slab.  When core holes were drilled to accommodate the DCP cone, the cores fell into the voids under the slab.
  • GPR readings are difficult in clayey soils, but shallow subsurface voids were detected, especially around the 12’ diameter brick manhole.
  • Penetrometer results, measured in blow counts, indicated very soft soils down to 28’ in some places.
  • Very soft soil was detected around the 12’ diameter brick manhole.

At this point, it was determined that the root cause of the slabs' and voids' settlement must be an infrastructure infiltration issue. Lift It Rite technicians met with Deas Construction on-site for a third visit to inspect the interior of the infrastructure.

Entry was made into a new manhole uphill beside the employee parking lot.  This manhole was connected to the 12’ diameter brick manhole (located in the area of settling) by a 72” corrugated metal pipe (CMP).  The CMP runs parallel to the back of the facility where the loading docks are located.  It is about 16’ deep (below grade of concrete) to the invert of the CMP.  Observations were as follows:

  • The CMP was in decent shape until you got closer to the area of the concrete slab settlement.
  • There were two major breaches in the CMP at the joints.  Soil was observed coming through the breaches.  These breaches were within the 75’ x 25’ rectangle of sunken concrete.
  • The inside of the 12’ diameter brick manhole was in pretty good shape except for the base itself, which was pitted and had voids underneath.

A summary of the testing and the walkthrough/site evaluation indicated that the failure of the 72” CMP culvert joints led to major soil erosion, which in turn led to settlement and undermining of the concrete. Additionally, the base of the 12” diameter brick manhole was pitted and broken, leading to more soil infiltration and settlement around the base.

Powerful Polymers

Lift It Rite employed a variety of specialized materials to address the complex issues at the site. AP Fill 700, manufactured by Alchatek, played a crucial role in sealing pipe joints and deep soil stabilization. This NSF/ANSI 61-approved polyurethane resin features a low viscosity for soil permeation and an impressive 30x expansion factor. Its ability to react with moisture creates a squeezing and compaction effect in the soil, making it ideal for sealing infiltration in stormwater and sewer systems and stabilizing roadways.

Lift It Rite used Alchatek’s AP Lift 475 high-density polyurethane foam for concrete lifting and void filling. This two-component system expands 15x its original volume, creating a strong, watertight support structure. The team used a PMC PHX-40 plural component proportioner capable of 4 gallons per minute output to apply this material. For the CIPP point repairs, Pelican Underground was called in to install fiberglass and felt composite liner impregnated with epoxy resin. This combination creates a structural repair that restores the pipe’s original strength. Lastly, AW Cook supplied a polymer-modified concrete patching material to rebuild and provide a new wearable surface for the brick manhole base.

Painless Procedures

A proposal was made for a three-step repair:

  • Lifting and void-filling the concrete slabs with high-density polyurethane.
  • Permeation and pressure grouting of the soils with single-component geotechnical hydrophobic polyurethane resin.
  • CIPP point repairs of the two breaches in the CMP and concrete repair for the 12’ diameter brick manhole base.

The proposal was accepted, and the work was done during September and October 2021.  The sequence of the work and details were as follows:

CMP (Corrugated Metal Pipe) Joint Injections and Soil Stabilization

Because of the amount of soil coming in through the failing CMP joints, Lift It Rite technicians decided it would be best to seal and encapsulate the joints with expanding polyurethane foam to create a temporary patch until the CIPP point repair contractor could mobilize.  This would stop the undermining of the concrete by eliminating the erosion pathways. 

The technicians went down through the 12’ diameter manhole and proceeded up the 72” CMP culvert to the failed joints.  At four locations, AP Fill 700 was injected in a clock pattern at the failed joints.  Injection holes were drilled through the wall of the CMP approximately 12” offset from the joint.  The resin was pumped until reacting polyurethane foam refused back through the joint breaches and sealed them off.  Once all the joints were sealed, the soil stabilization could proceed.

Two CMP pipe breaches and a brick manhole with infiltration issues occurred within a 75’ x 25’ area. DCP testing detected loose soil down to 28’ below grade. This CMP culvert had a constant flow of water through it, so the surrounding soils were wet and soft, and the soil infiltration into the CMP compounded this. The grout plan would involve permeation/compaction injections to stabilize this block of soil 75’ x 25’ x 28’ deep.

GCS performed additional GPR scanning before the soil stabilization grouting, and Ground Penetrating Radar Services came by to locate the water main and fire hydrant piping.

A grid pattern was laid out with approximately 3-5 foot spacing. Some spacing varied due to obstructions like the steel racks, etc. ABC Concrete Cutting was called in to core the 2” holes to accommodate the next step: forming the holes for the pressure grouting. Over 100 holes were cored in the 72’ x 25’ area.

Geotechnical Contractor GeoLab was called in to use Direct Push technology to form the grout holes with their Geoprobe machine.  Because of the clayey soils present, it was possible to press the holes using a 1-3/4” pressing tool and then extract the probe, leaving a 1-3/4” to 28’ deep hole pressed into the soil.  2” x 4’ long steel grout pipes were then hammered into the pressed holes to serve as grout pipes.  Each grout pipe was hammered 2-3 feet into the bored hole and then terminated at the top with a high-pressure valve and a quick connect.

The typical application rate for soil stabilization is around 1 gallon per vertical foot.  When the polyurethane resin is pumped into a pressed hole, the entire hole is pressurized, and the resin will find the weakest soil zones to penetrate and expand. AP Fill 700 was injected through the entire grid pattern of directly pushed holes using air-powered and gas-powered hydraulic-powered pumps. After 28 gallons were installed per point, the injections were stopped.  There was some contractor discretion on site if it was determined one point had looser soil and another area was tight.  A few holes could not be pumped because of the grout's migration, and the soil's compaction would cause an adjacent hole to be closed.  If a new pipe could be inserted there, the technicians would try and pump it, but typically, once a hole gets filled/squeezed shut, it becomes like rock in there, and the hole cannot be re-bored.

AP Fill 700 was also injected through ½” steel injection probes in a circumferential pattern around the 12’ diameter brick manhole.  These were extra injections in addition to the grid pattern to ensure the brick structure was sealed up and the soil around it compacted.  Looking down through the opening of the 12’ brick manhole, one can see the reacted grout permeating the loose brick walls.

Slab Lift and Void Fill

Slab lifting and void filling was done using AP Lift 475.  DOTs and geotechnical contractors use this type of structural polyurethane nationwide to lift concrete, support slabs, fill voids, and stabilize infrastructure.  The high-density poly is a two-component system with an A-side and a B-side chemical.  The reaction occurs when the two components meet, resulting in a high-density, watertight polyurethane foam.  This product expands 15x by volume, depending on conditions. The equipment used was a PMC PHX-40 plural component proportioner capable of 4 gallons per minute of output.

A grid pattern of approximately 4’ on center was drilled through the 75’ x 25’ slab. Injection holes were 3/8” in diameter. Each injection hole was checked with a probe before injecting poly, and in some areas, the technicians found voids up to 60”.  AP Lift 475 was injected beneath the concrete until the voids were filled and the lift was detected.  In areas requiring more lift, slab recovery was attempted with more injections.  Extra care was taken not to create too much lateral force when injecting around the brick manhole. 
A walk-behind concrete saw was brought in to cut the joints and free up binding slabs in the area where more lift was needed.  After the joints were freed, the technicians got more lift.  The 2” core and 3/8” injection holes were patched with concrete.

CIPP (Cured-In-Place Pipe) Point Repair

Pipe relining specialists from Pelican Underground were called in to perform point repairs on the two failed joints. They ultimately performed four-point repairs. One of the failed joints required two overlapped CIPP repairs. Additionally, they discovered and addressed an additional breach further up the pipeline.  
A CIPP point repair is a fiberglass and felt composite liner impregnated with epoxy resin and then pressed into the walls of the host pipe with pneumatic pressure.  A CIPP repair is a structural repair, not a patch.  That pipe is now as strong as new in those areas.

Before installing the point repair, a bypass pumping system was set up upstream from the repair work. Water was constantly flowing in this CMP, so it was dammed off and pumped (bypass) around the repair work area.  After the water was diverted, interior surface prep was performed.  This involved cleaning and removing AP Fill 700, which had permeated the pipe and coated the walls and floor, then pressing some of the jagged metal with hydraulics to bend it back into place as much as possible.  Sharp edges were also trimmed.

Once this was complete, the point repair liners were assembled.  They rolled out the fiberglass liner, coated it with epoxy, combined it with the felt liner, and then wrapped it around an inflatable packer.  That entire assembly was lowered through the manhole opening and pulled into place by the crew.  Compressed air was applied, and the packer expanded and pressed the CIPP liner into place.  The packer was then deflated and removed after the initial cure.  This was repeated for each point repair.

The brick manhole with the failing concrete base was then injected through the floor with polyurethane to fill any voids below it and provide support for rebuilding the base. Pelican Underground used a polymer-modified concrete patching material from AW Cook to fill any holes in the base and provide a new wearable surface for the concrete.

Rapid Results

Lift It Rite performed manual compaction testing by going through the 75’ x 25’ grid pattern with a ½” probe to see any loose soil zones.  With the manual probe, it was difficult to penetrate the ground, which indicated good compaction and void fill throughout the zone.

Ground Consolidation Services then brought back a dynamic cone penetrometer to do post-project DCP testing in the areas where testing had been done before. DCP results indicated a great increase in bearing capacity. A few shallow core samples were also taken and showed complete fill and compaction.

Ground-penetrating radar was then run along the same scan lines to compare before and after scans; those also showed improvement.

Parking Lot Stabilization 2

The Upper core sample showed high-density polyurethane that filled the void between the slab and subgrade.  The lower core is AP Fill 700 polyurethane binding gravel together.  There were areas of gravel encountered on site, and the permeation material glued it together into a solid mass.

Want more information on stabilizing soil with polyurethane?

Download an Info-Packed Soil Stabilization Brochure!

Topics: All Posts, Stabilize Soil

Limited Space Still Available - Alchatek 2024 Fall Geotech Training

Posted by Kreg Thornley on Oct 1, 2024 10:00:00 AM

Banner - 2024 Fall Geotech Training

Body - 2024 Fall Geotech Training-2Essential Details

Dates/Pricing

Geotechnical Masterclass: November 12th-14th, 2024 – $695.00
(Special pricing for all who register before October 7th at 5pm Eastern. $745 after.)

Location

To Be Determined
(in Georgia)

Discount

$50 discount for each additional participant.

Click Here to Register NOW!

Geotechnical Masterclass

Elevate your geotechnical expertise with our comprehensive masterclass covering cutting-edge techniques and solutions. Master:

  • Polyurethane Concrete Leveling for sunken slabs
  • Polyurethane Soil Stabilization for various soil types
  • Geotechnical Testing with precision
  • Deep Lock® soil stabilization procedures

Why Attend?

Gain Hands-On Experience with state-of-the-art equipment
Learn From Industry-Leading Experts with decades of experience
Network with Peers and potential collaborators
Boost Your Company’s Market Reach and capabilities

Consider the low cost of training vs. the high cost of job screw-ups and missed opportunities.

Transitioning from routine geotechnical work to more complex and high-stakes infrastructure and large-scale construction projects represents a significant growth opportunity for your career and business. Get the advanced skills and critical insights needed to tackle challenging projects and succeed in competitive markets confidently.

Join us for this transformative Geotechnical Masterclass. We’ll equip you with the knowledge and techniques to excel across all geotechnical project types.

Click Here to Register NOW!

Topics: All Posts, Lift Slabs, Stabilize Soil, Business Tips, Fill Voids, Deep Lock, Training, Municipal Resources, Events

Reminder - Register for Alchatek 2024 Fall Geotech Training

Posted by Kreg Thornley on Sep 23, 2024 10:00:00 AM

Banner - 2024 Fall Geotech Training

Body - 2024 Fall Geotech Training-2Essential Details

Dates/Pricing

Geotechnical Masterclass: November 12th-14th, 2024 – $695.00
(Special pricing for all who register before the end of September. $745 October 1st and later.)

Location

To Be Determined
(in Georgia)

Discount

$50 discount for each additional participant.

Click Here to Register NOW!

Geotechnical Masterclass

Elevate your geotechnical expertise with our comprehensive masterclass covering cutting-edge techniques and solutions. Master:

  • Polyurethane Concrete Leveling for sunken slabs
  • Polyurethane Soil Stabilization for various soil types
  • Geotechnical Testing with precision
  • Deep Lock® soil stabilization procedures

Why Attend?

Gain Hands-On Experience with state-of-the-art equipment
Learn From Industry-Leading Experts with decades of experience
Network with Peers and potential collaborators
Boost Your Company’s Market Reach and capabilities

Consider the low cost of training vs. the high cost of job screw-ups and missed opportunities.

Transitioning from routine geotechnical work to more complex and high-stakes infrastructure and large-scale construction projects represents a significant growth opportunity for your career and business. Get the advanced skills and critical insights needed to tackle challenging projects and succeed in competitive markets confidently.

Join us for this transformative Geotechnical Masterclass. We’ll equip you with the knowledge and techniques to excel across all geotechnical project types.

Click Here to Register NOW!

Topics: All Posts, Lift Slabs, Stabilize Soil, Business Tips, Fill Voids, Deep Lock, Training, Municipal Resources, Events

Register for Alchatek 2024 Fall Geotech Training

Posted by Kreg Thornley on Sep 5, 2024 11:06:34 AM

Banner - 2024 Fall Geotech Training

Body - 2024 Fall Geotech Training-2Essential Details

Dates/Pricing

Geotechnical Masterclass: November 12th-14th, 2024 – $695.00
(Special pricing for all who register before the end of September. $745 October 1st and later.)

Location

To Be Determined
(in Georgia)

Discount

$50 discount for each additional participant.

Click Here to Register NOW!

Geotechnical Masterclass

Elevate your geotechnical expertise with our comprehensive masterclass covering cutting-edge techniques and solutions. Master:

  • Polyurethane Concrete Leveling for sunken slabs
  • Polyurethane Soil Stabilization for various soil types
  • Geotechnical Testing with precision
  • Deep Lock® soil stabilization procedures

Why Attend?

Gain Hands-On Experience with state-of-the-art equipment
Learn From Industry-Leading Experts with decades of experience
Network with Peers and potential collaborators
Boost Your Company’s Market Reach and capabilities

Consider the low cost of training vs. the high cost of job screw-ups and missed opportunities.

Transitioning from routine geotechnical work to more complex and high-stakes infrastructure and large-scale construction projects represents a significant growth opportunity for your career and business. Get the advanced skills and critical insights needed to tackle challenging projects and succeed in competitive markets confidently.

Join us for this transformative Geotechnical Masterclass. We’ll equip you with the knowledge and techniques to excel across all geotechnical project types.

Click Here to Register NOW!

Topics: All Posts, Lift Slabs, Stabilize Soil, Business Tips, Fill Voids, Deep Lock, Training, Municipal Resources, Events

Case Study - Stabilizing a Quarter-Mile Stretch of a Three-Lane Highway

Posted by Kreg Thornley on Aug 29, 2024 10:00:00 AM

Banner-Stabilizing-a-Quarter-Mile-Stretch-of-a-Three-Lane-Highway

Body-Stabilizing-a-Quarter-Mile-Stretch-of-a-Three-Lane-HighwayAdministrators at Orange County, Florida Public Works had a pressing issue. Settlement was occurring along a quarter-mile stretch of a three-lane roadway. The culprit? Loose, sandy soils combined with a high water table. Before repaving could begin, stabilizing the supporting soil was crucial. This case study explores how the problem was addressed and resolved. This project showcases innovative solutions for common infrastructure challenges in areas with problematic soil conditions.

Powerful Polymers

AP Fill 700 was selected as the repair material for this project. Its low viscosity allowed for effective soil permeation, and its curing strength promised to create a permanent soil mass. These properties made AP Fill 700 the perfect choice for stabilizing the loose soil beneath the roadway. The selection of this material demonstrated the importance of choosing the right product for specific geotechnical challenges. AP Fill 700's unique characteristics ensured a robust and long-lasting solution.

Painless Procedures

A methodical approach was essential for this project. First, a large grid pattern for injections was carefully planned out. Each injection point was spaced five feet apart, and the depth of each injection reached approximately 15 feet. At each point, one gallon of material was injected per vertical foot. This systematic process ensured thorough coverage and stabilization of the problematic soil. The precise spacing and depth of injections were critical factors in the project's success. By following this detailed procedure, the team could address the soil instability comprehensively.

Rapid Results

This massive project was completed in about a week. As a result, the once-loose soil was successfully stabilized. The municipality now had a solid foundation to repave the quarter-mile stretch of road. In the end, Orange County Public Works had effectively addressed the settlement issue. The roadway was now ready for safe, long-lasting resurfacing. This efficient resolution solved the immediate problem and prevented potential future issues. The success of this project demonstrated the effectiveness of proactive infrastructure maintenance and the value of employing advanced soil stabilization techniques.

Want more information on soil stabilization with polyurethane?

Download an Info-Packed Soil Stabilization Brochure!

Topics: All Posts, Stabilize Soil

Case Study - Stabilizing a Historic Building with a Sandstone Foundation

Posted by Kreg Thornley on Aug 15, 2024 10:00:00 AM

Banner - Stabilizing a Historic Structure with a Sandstone Foundation

Body - Stabilizing a Historic Structure with a Sandstone FoundationIn Salt Lake City, Utah, a historic brick structure built in 1893 showed signs of foundation settlement. The building's sandstone foundation presented a challenge. Traditional stabilization methods like installing helical piers could potentially cause further damage. Rhino Foundation Systems proposed a solution using polyurethane foam to stabilize the foundation. This case study examines how this approach addressed the building's foundation problems.

Powerful Polymers

The technicians selected AP Lift 430 polyurethane foam for the project. This foam was chosen for its ideal soil stabilization and structural support properties. The plan involved injecting the foam beneath the footings to provide a stable support platform. This method would achieve the desired stabilization without requiring extensive excavation.

Painless Procedures

The project began with a detailed site assessment to understand the extent of the settlement and soil conditions. Following this, the team designed a plan to install 63 deep foam injections under the foundation, ensuring comprehensive coverage and stabilization. Specialized equipment was then used to perform these deep injections, with the foam strategically placed to improve the soil and stabilize the foundation.

Rapid Results

The project delivered several key benefits. Deep foam injections improved the soil and provided a strong platform for the foundation, ensuring effective stabilization. The non-invasive process precluded the need for extensive excavation, preserving the structure and minimizing disruption. Notably, the project was completed in just two days, significantly reducing downtime and disturbance to the area. Finally, the polyurethane foam injections offered a cost-effective solution compared to traditional stabilization methods, making it an economically viable option for similar foundation challenges.

Want more information on soil stabilization with polyurethane?

Download an Info-Packed Soil Stabilization Brochure!

Topics: Stabilize Soil, Deep Lock

Case Study - Swimming Pool Stabilization and Lifting

Posted by Kreg Thornley on Aug 13, 2024 10:00:00 AM

Banner-Graphic-Swimming-Pool-Stabilization-and-Lifting

Body-Graphic-Swimming-Pool-Stabilization-and-LiftingThe management team at a community pool in Midvale, Utah, faced a significant challenge. A water leak had saturated the silty soil beneath the structure, causing uneven settlement and safety hazards. To address this issue, they brought in geotechnical specialists from Rhino Foundation Systems, who proposed an innovative solution as an alternative to tearing out and replacing the pool. This approach not only promised to stabilize the pool but also lift it back to its proper position.

Powerful Polymers

The key to this solution was Alchatek's AP Lift 440 polyurethane foam. This powerful polymer was chosen for its soil stabilization, load-bearing, and lifting capabilities. Deep soil injections were planned to address the underlying issues. The foam's expanding properties would displace water and stabilize the soil base. This method offered a non-invasive alternative to traditional approaches like helical piles.

Painless Procedures

The process began with a thorough site assessment. The technicians analyzed soil saturation and settlement patterns. Based on this data, a 3-foot by 5-foot injection grid was designed. Next, holes were drilled through the bottom of the pool, and injection rods were installed. AP Lift 440 was injected beneath the structure. As a result, the expanding foam displaced water and stabilized the soil base. Following this, the pool was lifted by 3.5 inches. Finally, the pool deck was adjusted to match the new level.

Rapid Results

The pool was successfully stabilized and leveled with minimal disruption. Moreover, there was no need for extensive excavation. This method proved to be both effective and efficient. The foam injections effectively displaced water and stabilized the soil. Additionally, the lifting process was precise, raising the pool by exactly 3.5 inches. Perhaps most importantly, this solution was cost-effective. It proved quicker and more economical than complete pool replacement.

Want more information about lifting and stabilization with polyurethane?

Download an Info-Packed Slab Lift Brochure!

Download an Info-Packed Soil Stabilization Brochure!

Topics: All Posts, Lift Slabs, Stabilize Soil, Deep Lock

Case Study - Manhole Soil Stabilization and Infiltration Repair

Posted by Andy Powell on Aug 8, 2024 10:00:00 AM

Banner - Manhole Soil Stabilization and Infiltration Repair

Body - Manhole Soil Stabilization and Infiltration RepairManhole infiltration can pose serious risks to nearby structures. In a recent case, water infiltration pulled soil into a manhole, eroded the ground beneath a walkway in front of a residence, and threatened to compromise the home's foundation. Specialists from SiteMix Pressure Grouting, LLC were called in to perform repairs to address this urgent situation.

Powerful Polymers

Two key products were selected for the job. First, AP Fill 700 was chosen to stabilize the soil around the manhole and seal the leaks. This product features low viscosity, making it ideal for permeating soil and sealing thin cracks. Additionally, it activates with moisture, which is perfect for damp environments like this one. Secondly, AP Lift 430 was selected to stabilize the house's footing. This high-density product cures quickly. Furthermore, it excels at filling voids and stabilizing soil near structures due to its high load-bearing capacity.

Painless Procedures

The repair process began with stabilizing the soil around the manhole. To achieve this, injection rods were driven into the ground around the structure. Then, AP Fill 700 was injected to seal the leaks and stabilize the surrounding soil. Next, the team focused on the large void areas around the house's footing. Once again, injection rods were utilized. This time, AP Lift 430 was injected to fill the voids and secure the foundation.

Rapid Results

The repair project yielded impressive outcomes. First and foremost, the manhole was successfully sealed. In addition, the surrounding soil was stabilized, preventing further erosion. The walkway, previously at risk, was now secure. Importantly, the voids adjacent to the house were filled, protecting the foundation. Remarkably, all these tasks were completed in less than a day. Finally, the repaired area was prepared for the county to add backfill around the newly stabilized manhole. This swift and effective solution ensured the safety of both the property and its residents.

Want more information on stabilizing soil with polyurethane?

Download an Info-Packed Soil Stabilization Brochure!

Topics: All Posts, Seal Leaks, Stabilize Soil