The Cave Buttes Dam, located in Phoenix, Arizona, required modifications that involved installing a 60-inch diameter steel conduit pipe beneath the dam through bedrock. During tunneling operations, a 15-foot-wide fault zone containing water and composed of clay was encountered. After the excavation and grouting of the annular space between the pipe and the rock with cementitious grout, leaks began to emerge from some of the welded grout packer plugs. SSC Underground was the contractor for this project, with engineering oversight provided by AECOM and the U.S. Army Corps of Engineers.
Initial Assessment
The primary issue was leaking grout plugs, which were 2-inch diameter, straight-threaded plugs welded into place after the initial grouting process. These plugs exhibited varying degrees of water seepage, with flow rates estimated at a few gallons per minute. The leaks were attributed to anticipated movement between the steel pipe and the surrounding rock due to temperature changes and vibrations. Based on these conditions, a flexible chemical grout was determined to be the best solution to seal the leaks while accommodating future movement.
Proposed Solution
Alchatek recommended injecting Spetec PUR F400, a flexible polyurethane grout, to seal the leaks. This grout was selected because of its ability to bond effectively while maintaining flexibility to withstand differential movement between the steel pipe and surrounding materials. The plan involved drilling into the existing grout plugs and injecting Spetec PUR F400 through packers to confine the grout and ensure a complete seal. The project utilized packers for controlled injection and a Titan Impact 440 pump to deliver the grout. Alchatek Gen Cat was used to manage the grout’s reaction time based on the specific site conditions.
Procedures
1. Preparation:
- The team drilled into the center of each leaking grout plug to create access points for injection.
- Packers were installed into these drilled holes to facilitate the controlled injection of the grout.
2. Injection Process:
- Spetec PUR F400 was injected through the packers using a Titan Impact 440 pump.
- Alchatek Gen Cat was added to the grout mixture to adjust reaction times as needed.
- The injection process was monitored to ensure proper confinement of the grout within the leaking areas.
3. Post-Repair Monitoring:
- After sealing each leaking port, inspections were conducted to confirm the cessation of water infiltration.
- New leaks that emerged from previously sealed or new locations were identified for subsequent treatment.
Results and Conclusion
The initial injection process sealed most of the identified leaking grout ports, effectively stopping water infiltration at those locations. However, water subsequently found new paths, resulting in additional leaks from previously sealed ports. The team used the same materials and procedures to address these additional leaks through follow-up injections. Ultimately, all leaks were successfully sealed, restoring the integrity of the steel pipe installation.