Looking for a Contractor?
Looking for a Contractor?

Alchatek Blog

Landon Feese

Recent Posts

Case Study - Airport Runway Lifted and Stabilized in Hours Without Shutdown

Posted by Landon Feese on Dec 11, 2025 10:00:01 AM

Banner - Airport Runway Lifted and Stabilized in Hours Without Shutdown

Body - Airport Runway Lifted and Stabilized in Hours Without ShutdownAt Antwerp Airport, a section of the runway slab had settled by 1–2 inches, creating a hazardous rocking effect that endangered aircraft landing gear and led to grounded flights. Aircraft wheels hitting the depressed area like a pothole generated dangerous jolts. Although the settlement had persisted for years, mounting operational demands finally compelled immediate action.

Initial Assessment

Initial investigations revealed voids beneath the 8-inch-thick concrete slab. Replacing the entire slab proved impractical because it would require a multi-day runway shutdown, extended project timelines, and substantially higher costs.

Proposed Solution

The contractor selected Alchatek’s AP Lift 430 polyurethane foam for its hydro-insensitivity, rapid strength development, 22x expansion ratio, and compressive strength of 7,200 psf. These properties enabled efficient lifting and stabilization with minimal downtime.

Procedures

  1. Marked the slab and established 8 injection points in a grid pattern.
  2. Drilled through the 8-inch slab and installed injection ports.
  3. Injected 16 gallons of AP Lift 430 in staged passes.
  4. Monitored elevations with dial indicators.
  5. Sealed the drill holes and restored the surface.

Results

  • The slab was lifted to specifications, resulting in zero differential settlement with adjacent panels.
  • The project was completed in just 4 hours—over 90% faster than a full slab replacement.
  • The international airport resumed its full flight schedule the same day, avoiding over $100,000 in losses from runway closures.

Want more information on lifting slabs with polyurethane?

Download an Info-Packed Slab Lift Brochure!

Topics: All Posts, Lift Slabs

Case Study - Rapid Interior Rescue with AP Lift 440

Posted by Landon Feese on Dec 10, 2025 10:00:00 AM

Banner---Rapid-Interior-Rescue-with-AP-Lift-440

Body---Rapid-Interior-Rescue-with-AP-Lift-440A single-story office building settled over organic soils beneath its post-tensioned slab. With access restricted to the interior, a fast and clean repair was essential. Geotech experts from Helicon were called in to assess the situation.

Initial Assessment

Borings showed dense to very loose strata and differential movement under interior columns and slab zones; uniform densification and code‑level lift tolerance were required. Traditional underpinning inside an occupied shell would extend schedules and raise costs versus targeted polyurethane injection.

Proposed Solution

The contractor selected AP Lift 440 for hydro‑insensitivity, rapid reaction, and ~80 psi compressive strength. This material was ideal to permeate, densify, and lift with minimal downtime.

Procedures

  1. Inject 30,000 lbs over 635 interior points per geotech layout.
  2. Apply tight grid spacing, pressure/volume control, and real‑time elevation checks.
  3. Coordinate QA/QC with the Engineer of Record for sign‑offs.

Results

  • Restored slab support and column bearing
  • Zero exterior disruption; interior‑only access.
  • Approximately 97% cost savings vs interior underpinning/piering, with faster completion.

Want more information on polyurethane concrete leveling?

Download an Info-Packed Slab Lift Brochure!

Topics: All Posts, Lift Slabs

Case Study - Minimally Invasive Tunnel Leak Repair

Posted by Landon Feese on Dec 3, 2025 10:00:02 AM

Banner - Minimally Invasive Tunnel Leak Repair

Body - Minimally Invasive Tunnel Leak RepairA critical downtown Houston pedestrian tunnel had persistent water infiltration affecting the ceiling, walls, and floor throughout the structure. The tunnel serves as vital underground infrastructure in Houston's urban core, where any significant disruption would impact pedestrian traffic and building access. Initial observations revealed widespread moisture intrusion, but the full extent of the problem remained unclear until interior finishes could be removed for proper assessment. The facility required a rapid, effective solution that would minimize downtime and restore the tunnel's watertight integrity.

Initial Assessment

Once sheetrock was removed from affected areas, engineers discovered extensive water infiltration through multiple pathways in the concrete structure. Moisture intrusion was occurring through joints, cracks, and penetrations, creating a complex leak pattern that compromised the tunnel's structural integrity and usability. Traditional repair methods would have required extensive excavation from above or complete tunnel closure for membrane installation - both prohibitively disruptive options in Houston's dense downtown corridor. The assessment revealed that targeted injection could address the root cause of infiltration without major structural modifications.

Proposed Solution

Alchatek recommended using Spetec PUR GT350, a hydrophilic polyurethane grout specifically designed for active leak sealing in underground structures. This single-component material was selected for its ability to react with water to form an expanding, flexible foam that creates a permanent, waterproof barrier. The injection approach would allow precise targeting of leak sources while maintaining tunnel accessibility throughout the repair process. The polyurethane's expansion properties would ensure complete void filling and crack sealing, even in areas with irregular geometries or active water flow.

Procedures

  1. Mapped all visible leak points and moisture intrusion areas throughout the tunnel structure.
  2. Drilled strategic injection ports at locations determined to intercept water infiltration pathways.
  3. Injected polyurethane grout through ports using positive displacement pumps, monitoring for material refusal and leak cessation.
  4. Conducted systematic injections across all identified problem areas, adjusting techniques based on local conditions.
  5. Verified complete sealing through visual inspection and moisture monitoring following cure completion.

Results

The polyurethane injection process successfully eliminated water infiltration throughout the tunnel structure, restoring its watertight integrity without requiring facility closure or major structural modifications. Post-treatment inspections confirmed the complete cessation of leaks, with the tunnel remaining dry even during subsequent heavy rain events. The minimally invasive approach allowed the tunnel to remain operational throughout the repair process, avoiding costly service interruptions. For a typical tunnel section, this represents over 95% cost savings compared to traditional methods. Additionally, avoiding tunnel closure prevented an estimated $10,000 to $ 25,000 in daily economic losses due to disrupted pedestrian traffic and building access, further amplifying the financial benefits of this innovative approach.

Want more information about polyurethane crack injection?

Download an Info-Packed Crack Injection Brochure!

Topics: All Posts, Seal Leaks, Crack Injection

Case Study - Tunnel Crack Repair with Expanding Grout

Posted by Landon Feese on Nov 19, 2025 9:59:59 AM

Banner Graphic Tunnel Crack Repair with Expanding Grout

Body Graphic Tunnel Crack Repair with Expanding GroutA tunnel structure in the Mobile, Alabama area had persistent water infiltration at the interface between concrete and metal components. The leak was traced to a tight crack at the joint, allowing water to migrate into the tunnel and cause visible staining, as well as potential long-term deterioration. The client sought a solution that would seal the leak without requiring major demolition or extended tunnel closure.

Initial Assessment

Visual inspection and on-site review identified the leak path at the interface between the concrete and metal. The crack width was measured between 0.2 and 0.3 mm, indicating that traditional cementitious grouts or surface sealants would not be effective. The challenge was to deliver a material that could penetrate deep into the joint and expand to form a watertight seal, even in confined spaces and around embedded metal.

Proposed Solution

Alchatek recommended Spetec PUR F400, a low-viscosity, hydrophobic polyurethane grout. Its ability to penetrate narrow cracks and react with water creates a durable, flexible seal. The product’s flow characteristics made it ideal for tight joints, and its expansive properties ensured comprehensive coverage within the voids and cracks. The injection plan called for drilling at the locations marked on the provided site photos, angling back toward the metal at approximately 18 inches deep to intersect the leak path.

Procedures

  1. Identified injection points along the crack, using red-dot markings on the structure as a guide.
  2. Drilled holes at 45° angle 12-inches apart, reaching approximately 18 inches deep to intersect the metal interface.
  3. Injected Spetec PUR F400 polyurethane grout through the drilled ports, using a pump setup suitable for low-viscosity materials.
  4. Monitored for material refusal and evidence of grout migration to ensure the joint was fully saturated and sealed.
  5. Continued injection until the crack would not accept additional material, confirming a complete watertight barrier.

Results

The injection process successfully sealed the tunnel leak at the concrete-to-metal interface. The approach allowed for precise targeting of the leak path, with minimal disturbance to the tunnel structure and no need for extended closure or demolition. The client was able to resolve the water infiltration efficiently, reducing the risk of future deterioration and avoiding the significantly higher costs and downtime associated with traditional excavation or membrane replacement. This project demonstrates the effectiveness of modern polyurethane injection in addressing challenging below-grade leak scenarios, particularly where access is limited and the leak path is confined.

Want more information about sealing cracks with polyurethane?

Download an Info-Packed Crack Injection Brochure!

Topics: All Posts, Seal Leaks, Crack Injection

Case Study - Smart Solution Saves Luxury Pool Deck

Posted by Landon Feese on Nov 12, 2025 10:00:02 AM

Banner - Smart Solution Saves Luxury Pool Deck

Body - Smart Solution Saves Luxury Pool DeckAfter the removal of a wooden deck, dangerous voids under the brick pavers were revealed in a luxury apartment pool deck, threatening its integrity and safety. The property owner contacted Helicon, a trusted foundation repair company.

Initial Assessment

Subsurface investigation confirmed extensive voiding with no practical access for excavation during occupancy. Demolition/replacement would take weeks, cost tens of thousands, and the pool would need to be closed during peak season.

Proposed Solution

The contractor selected AP Lift 440 for its hydro‑insensitivity, ~15‑minute cure, and ~80 psi compressive strength. This material was ideal for increasing the soil's bearing capacity and restoring the pool to its correct state.

Procedures

  1. Map the void locations using ground-penetrating radar and probing.
  2. Establish an injection grid targeting the largest voids first.
  3. Drill strategic injection ports through pavers to void spaces.
  4. Inject AP Lift 440 to refusal using calibrated pressure monitoring.
  5. Allow 15-minute cure
  6. Seal injection ports and restore surface aesthetics.

Results

  • Structural integrity fully restored with 1,200 lbs of AP Lift 440, filling all voids.
  • Zero operational downtime; pool deck remained accessible throughout repair.
  • Approximately 70-90% cost savings compared to demolition/replacement alternatives.

Want more information on Alchatek geotechnical products?

Download the Info-Packed Geotech Product Catalog!

Topics: All Posts, Fill Voids

Case Study - Tennessee State Prison: Rapid Void Filling Solution

Posted by Landon Feese on Nov 5, 2025 10:00:03 AM

Banner Graphic Tennessee State Prison

Body Graphic Tennessee State PrisonA Tennessee state correctional facility had a significant infrastructure failure when newly installed plumbing beneath a concrete slab malfunctioned. In an attempt to address the issue, the original contractor backfilled the entire plumbing system with concrete. When this approach proved unsuccessful, a second contractor was brought in to demolish the concrete and properly repair the plumbing systems. This process left a substantial void beneath the slab that required immediate filling to restore structural integrity and minimize facility downtime.

Initial Assessment

Following the plumbing repairs, engineers assessed a void measuring approximately 200 square feet in area and 4-5 feet in depth, totaling roughly 800-1,000 cubic feet of empty space beneath the concrete slab. The prison's security restrictions severely limited access to equipment, making traditional concrete replacement a challenging and time-consuming process. The facility required a solution that would minimize disruption to operations while providing structural support equivalent to the original concrete base.

Proposed Solution

Working with Alchatek, Mid-South Concrete Lifting recommended using  AP Fill 420, a two-component structural polyurethane foam, to fill the substantial void. This approach offered several critical advantages for the correctional facility environment. The material could be applied through a simple hose system, eliminating the need for heavy concrete trucks and mixing equipment that would be difficult to maneuver through security checkpoints. The foam's rapid curing time would significantly reduce the project timeline, and its structural properties would provide adequate load-bearing capacity for the slab above.

Procedures

  1. Security clearance and equipment inspection were completed to bring polyurethane application equipment into the facility.
  2. The void was accessed through existing openings created during the concrete removal process.
  3. AP Fill 420 was applied using a free-shooting technique.
  4. Material application was monitored to ensure complete filling and proper expansion throughout the space.

Results

The void filling was completed in 3 hours versus an estimated week for concrete replacement. AP Fill 420 polyurethane foam successfully filled the entire void space and provided adequate structural support. Prison officials expressed satisfaction with the efficiency and minimal operational disruption, leading the contractor to look at another similar project at a different state facility.

The polyurethane approach delivered 65-75% cost savings compared to traditional concrete replacement when accounting for materials, equipment, labor, and reduced facility disruption. The accelerated timeline also eliminated the extended security coordination costs typically associated with longer construction projects.

Want more information on geotech products and equipment?

Download the Info-Packed Geotech Product Catalog!

Topics: All Posts, Fill Voids

Case Study - Rapid Condo Foundation Lift with AP Lift 440

Posted by Landon Feese on Oct 29, 2025 9:59:59 AM

Banner---Rapid-Condo-Foundation-Lift-with-AP-Lift-440

Body---Rapid-Condo-Foundation-Lift-with-AP-Lift-440Fifteen, two‑unit condominium buildings exhibited differential settlement and interior slab movement from loose organics and voiding, risking structural performance and livability. Continuous occupancy required a rapid, low‑disruption remediation strategy that delivered durable lift and stabilization. The job was completed by foundation repair specialists at Helicon.

Initial Assessment

Investigations confirmed loose to very loose near‑surface soils, voids at 3–8 ft below the surface, and active settlement beneath slabs and footings under service loads; full replacement was not viable due to resident displacement, extended schedules, and higher cost risk.

Proposed Solution

The experts at Helicon selected AP Lift 440 for its hydro‑insensitivity, rapid reaction, and ~80 psi compressive strength to permeate, densify, and lift with minimal downtime.

Procedures

  1. Grid the interiors; mark piles, grout points, and quality control benchmarks.
  2. Inject low‑mobility compaction grout to seal limestone and pre‑densify.
  3. Install underpinning to ~36 ft, using predrill/sleeves to bypass clays.
  4. Inject AP Lift 440 at 8/5/3 ft below land surface to lift slabs and encapsulate organics.
  5. Monitor elevations/pressures; proof‑load and video‑verify.

Results

  • Restored slab elevations and footing support with no resident displacement.
  • Completion in days to weeks vs months for replacement.
  • Approximately 80-90% cost savings versus full demolition/rebuild approaches.
  • Durable, closed‑cell, water‑resistant stabilization for long‑term performance.

Want more information on polyurethane slab lifting?

Download an Info-Packed Slab Lift Brochure!

Topics: All Posts, Lift Slabs, Stabilize Soil

Case Study - Instant Roadway Rescue with AP Lift 475

Posted by Landon Feese on Oct 22, 2025 10:00:00 AM

Banner - Instant Roadway Rescue with AP Lift 475

Body - Instant Roadway Rescue with AP Lift 475A south Georgia roadway developed a sinkhole over a double 48-inch RCP storm line about 10 feet deep, threatening lane safety and mobility. Replacement costs were prohibitive and would require extended closure and excavation.

Initial Assessment

The pipe exhibited joint leakage and surrounding soil loss, creating voids under pavement and shoulder with settlement risk across the travel path. Traditional open-cut replacement would demand deep shoring, traffic detours, and high restoration costs, making trenchless stabilization preferable. SiteMix Pressure Grouting LLC was called in to do the work.

Proposed Solution

The contractor selected AP Lift 475 for hydrophobic chemistry, industrial strength, and rapid set to encapsulate pipe exteriors, seal soil paths, and rebuild bearing capacity with minimal downtime.

Procedures

  1. Lay out three rows on 3-foot centers around both barrels.
  2. Inject at 6 lb per vertical foot to refusal for soil reconsolidation.
  3. Pull the injection tubing vertically while injecting to form grout columns.
  4. Encapsulate/seal pipe perimeter and monitor lift response.
  5. Verify surface support and closure readiness.

Results

  • Completed in one day with 1,400 lbs placed; roadway lifted and voids eliminated.
  • Zero excavation and minimal traffic disruption during work.
  • Approximately 95% cost savings compared to pipe replacement.

Want more information on lifting slabs with polyurethane?

Download an Info-Packed Slab Lift Brochure!

Topics: All Posts, Lift Slabs

Case Study - Zero-Excavation Driveway Recovery via Poly Permeation Grout

Posted by Landon Feese on Oct 15, 2025 10:00:02 AM

Banner - Zero-Excavation Driveway Recovery via Poly Permeation Grout

Body - Zero-Excavation Driveway Recovery via Poly Permeation GroutA fire station access roadway developed cracking from subsurface voids caused by storm drain seam gaps that washed out soil during heavy rain, threatening daily emergency operations and pavement integrity. Geotech specialists from Helicon were brought in to assess the situation.

Initial Assessment

CCTV and probing identified voids up to several inches beneath the asphalt and open joints along the drain, allowing soil migration. Excavation replacement was rejected due to weeks-long closure risk, higher cost, and potential future seam misalignment, making trenchless permeation grouting the viable path.

Proposed Solution

AP Fill 700 was chosen for hydrophobic, single‑component injection with very low viscosity, and adjustable cure, enabling soil permeation, joint sealing, and formation of a water‑tight bearing layer for traffic.

Procedures

  1. Map defects and mark the injection grid along the pipe and pavement.
  2. Drill ports; set packers to target joints and halo around pipe.
  3. Inject AP Fill 700 to refusal, prioritizing seam sealing.
  4. Permeate surrounding soils to fill voids and densify subgrade.
  5. Monitor pressures/returns; adjust set times for water presence.
  6. Verify with sounding/CCTV and traffic proof-load.

Results

  • Restored structural support and sealed joints with zero operational downtime.
  • Completion in days vs weeks.
  • Approximately 95% cost savings compared to full excavation and pipe replacement.

Want more information on geotech products?

Download the Info-Packed Geotech Product Catalog!

Topics: All Posts, Fill Voids

Case Study - Parking Structure Ceiling Leak Repair

Posted by Landon Feese on Oct 8, 2025 10:00:00 AM

Banner - Parking Structure Ceiling Leak Repair

Body - Parking Structure Ceiling Leak RepairA multi-level parking facility in downtown Los Angeles was experiencing significant water infiltration through its concrete ceiling. Building management had noticed increasing water staining and active leakage, particularly following rain events. The water migration around electrical conduits and light fixtures was most concerning, creating potential safety hazards with the electrical systems. Previous attempts to seal the ceiling using conventional surface treatments had failed to resolve the issue. With the structure serving high-end retail clients, the property management company required a solution to effectively stop the leaks while minimizing disruption to the facility's daily operations.

Initial Assessment

Inspection revealed that water was infiltrating through microscopic pathways in the concrete, with particularly noticeable intrusion around embedded conduits and penetrations. Engineers determined that concrete shrinkage had created tiny void spaces around these penetrations, some measuring only thousandths of an inch. Water was following these pathways, traveling along the outside of conduits and emerging at light fixtures and junction boxes installed in the ceiling. The ceiling showed distinctive water staining patterns radiating from these fixtures, confirming the migration pathway. Traditional polyurethane grouts would be too viscous to effectively penetrate these extremely small void spaces, requiring a material with exceptional flow characteristics.

Proposed Solution

Alchatek recommended using a specialized acrylic resin, Spetec AG 200. This material was selected specifically because of its extraordinarily low viscosity, significantly thinner than polyurethane alternatives, allowing it to travel through microfractures and voids that water could penetrate. Unlike thicker injection materials, acrylic resin can follow the same migration pathways as water, creating a waterproof barrier precisely where needed. The material's ability to travel long distances from injection points would minimize the number of injection ports required, reducing ceiling penetrations while ensuring complete sealing coverage around electrical conduits and other vulnerable areas.

Procedures

  1. Technicians identified and mapped all water intrusion points in the ceiling, identifying migration patterns to determine optimal injection locations.
  2. Strategic drilling and port installation were performed at intervals designed to intercept the water pathways, with particular focus on areas around electrical conduits.
  3. Ports were installed in a pattern that would allow the low-viscosity material to flow along the same paths as the water infiltration.
  4. Acrylic resin was injected through the ports, with continuous monitoring for material appearance at distant locations.
  5. Injection continued at each port until the material was observed emerging from adjacent ports or known leak points, confirming pathway filling.
  6. Engineers carefully monitored electrical systems throughout the process to ensure no disruption to the building's operations.

Results

The injection program successfully sealed the water infiltration pathways throughout the parking structure ceiling. Post-treatment monitoring through several significant rain events confirmed that all previously active leaks had been eliminated, with no further water migration observed around electrical fixtures. Most importantly, the acrylic resin's exceptional flow characteristics allowed for complete sealing with minimal disruption to the facility's operation. The property management company avoided spending an estimated $80,000-$100,000 that more invasive remediation methods would have required, while eliminating potential liability from water contact with electrical systems. The parking facility remained operational throughout the repair process, avoiding revenue loss that would have resulted from traditional ceiling replacement or excavation of the deck above.

Want more information about leak seal products?

Download the Info-Packed Leak Seal Product Catalog!

Topics: All Posts, Seal Leaks, Crack Injection