
Water infiltrated beneath spillway slabs at a campground, eroding soil and creating voids that cracked concrete. Leaks surfaced through cracks, threatening structural integrity. SiteMix Pressure Grouting, LLC was called in to repair the damage.
Initial Assessment
Probing revealed extensive voids beneath spillway slabs where water removed supporting soil and destabilized the structure. Traditional tear-out and replacement demanded extended closure, heavy equipment access, and prohibitive costs for this operational facility.
Proposed Solution
AP Lift 440 proved the perfect solution, featuring an 18x expansion ratio, 11,520 psf compressive strength for slab stabilization, and hydrophobic properties to prevent water infiltration.
Procedures
- Established 4-foot grid pattern at lowest spillway area.
- Drilled injection points through slabs.
- Injected AP Lift 440 systematically across grid.
- Monitored foam spread between injection points.
- Completed both spillway sides plus access ramps.
Results
Completed repair in two days with zero downtime.
Stabilized slabs and eliminated all water intrusion with visible concrete drying confirming effectiveness.
Achieved approximately 65% cost savings compared to traditional concrete replacement while avoiding weeks of disruptive demolition.



An interior elevator pit needed for ADA retrofit in a multi‑level building, inside an old stairwell beside a load‑bearing wall on sandy soils. Conventional shoring wasn’t feasible indoors with tight footprint and headroom limits. 

A below-grade warehouse loading ramp had water infiltration at the slab-to-wall cold joint. Hydrostatic pressure forced water and sandy soil through the joint during rainfall, clogging the French drain and requiring manual removal after each storm.

Developers working on a new CVS Pharmacy in Orlando, Florida, encountered critical soil stability issues during the construction process. The project managers faced a significant challenge when geotechnical testing revealed unsuitable soil conditions between 5 and 10 feet below the surface, posing a threat to the structural integrity of the planned parking lot. This issue was discovered after site preparation had already begun, adding urgency to finding an effective solution that would allow construction to proceed on schedule.
A municipal wastewater treatment facility in New York had catastrophic water loss in five interconnected tanks, including two Sequencing Batch Reactors (SBR) and a digester. One SBR alone lost 20–22 inches of water daily, threatening its compliance with environmental regulations and risking $25,000/day in regulatory fines. The facility’s partially buried concrete structure was built just five years prior, with cracks linked to defective cold joints and curing errors. Traditional demolition/replacement was estimated at $1.5M, but the client sought a less expensive and minimally invasive solution to avoid shutdowns. 

A public park in New York had critical erosion issues at its waterfront staircase and adjacent beach, which were built over a landfill. Over the years, natural erosion pulled back sand, exposing uneven foundation areas and creating safety hazards for visitors. The partially buried concrete staircase exhibited significant subsidence and shifting soil, posing a threat to structural collapse. The New York City Parks Department required a rapid solution to stabilize the site before further degradation occurred.
AT&T Plaza in downtown Dallas had persistent water infiltration issues in its basement and sub-basement levels, resulting in structural concerns and operational disruptions. The building's below-grade concrete walls developed multiple active leaks, allowing groundwater to penetrate the structure and causing dampness at wall-floor transitions, which raised concerns about potential corrosion of the reinforcing steel. Building management required an immediate solution that would effectively seal the leaks while minimizing disruption to commercial operations.
A persistent water infiltration was observed in a below-grade tunnel in Houston, TX. Staining on the sheetrock ceiling indicated the leak originated at the joint between the tunnel shell and the building wall, specifically at the interface with the flashing. The tunnel was situated on the negative pressure side of the structure, resulting in recurring water intrusion issues. The property management team sought technical advice to resolve the leak without extensive demolition or disruption to the building’s operations.
At Antwerp Airport, a section of the runway slab had settled by 1–2 inches, creating a hazardous rocking effect that endangered aircraft landing gear and led to grounded flights. Aircraft wheels hitting the depressed area like a pothole generated dangerous jolts. Although the settlement had persisted for years, mounting operational demands finally compelled immediate action.

A single-story office building settled over organic soils beneath its post-tensioned slab. With access restricted to the interior, a fast and clean repair was essential. Geotech experts from 