Looking for a Contractor?
Looking for a Contractor?

Alchatek Blog

Landon Feese

Recent Posts

Case Study - Warehouse Slab Leveling

Posted by Landon Feese on Mar 5, 2025 10:00:00 AM

Banner-Warehouse-Slab-Leveling

Body-Warehouse-Slab-LevelingThe owner of a gas manufacturing facility contacted a Georgia-based contractor regarding significant floor settlement issues, with a warehouse slab dropping approximately 3-4 inches. The settlement made issues for the forklift traversing in and out of the warehouse and posed a risk to the workers.

Initial Assessment

Upon arrival at the site, the team conducted a thorough investigation. Using a probe, voids were identified beneath the slab, with the probe sinking up to 2 feet in some areas. A Dynamic Cone Penetrometer test revealed large voids 2-4 feet below the slab.  Poor drainage was evident, with improper crowning causing water to flow towards the building instead of away from it. Interestingly, a layer of unusually hard clay was noticed outside the building, suggesting possible prior remediation attempts.

Proposed Solution

AP Lift 430 was chosen for this project, providing an excellent injectable polyurethane grout solution. With its impressive 22x expansion capability and 7,200 psf compressive strength, it’s ideal for warehouse slabs that support heavy equipment. The grout’s hydrophobic properties ensure long-term stability by blocking water infiltration that could otherwise lead to void formation.

image-png-Nov-01-2024-01-47-59-8883-PM

Procedures

1. Deep Injection (Void Fill)

  • 32 injection points were established in a grid pattern (16 on each side) at 4 ft apart.
  • At each point, the team injected 15-20 pounds of material at about 5 feet depth.
  • A slight lift (approximately 1/16 inch) during this phase indicated successful void filling.

2. Slab Lifting

  • Additional holes were drilled next to the wall, 3 feet from the wall, and 9 feet from the wall (6 feet from the first row).
  • Injection began from the holes nearest to the wall and moved outward.
  • Multiple passes were made, with some areas requiring 3-4 injections.
  • Gradual lifting was employed to prevent slab cracking.
  • Dial indicators were used to ensure even lifting across the warehouse floor.

Results

The project successfully stabilized the warehouse floor and restored it to its proper level. Effective void-filling addressed the underlying instability, providing a solid foundation for the slab. Success was evident in the restored functionality of the warehouse space and the elimination of safety hazards posed by the uneven floor. The property manager was pleased with the work and requested additional slab lifting services for their other facilities.

Want more information on lifting slabs with polyurethane?

Download an Info-Packed Slab Lift Brochure!

Topics: All Posts, Lift Slabs, Stabilize Soil, Fill Voids

Case Study - Apartment Complex Foundation Void Fill

Posted by Landon Feese on Jan 15, 2025 10:00:00 AM

Banner - Apartment Complex Foundation Void Fill

Body - Apartment Complex Foundation Void FillThe owners of a college apartment complex in Georgia reached out to a local engineering firm after discovering a large void underneath the northwest end of the building. The issue was caused by stormwater collecting and flowing beneath the building's foundation. Over time, the foundation became exposed and now the grade has lowered by a foot from the original design.

Site Investigation and Initial Attempts

A dynamic cone penetrometer test revealed the soil was fragile, with two to three blow counts for the tested areas. Underpinning piles had been installed by the previous owner, but did not did not adequately stabilize the building's foundation. The shifting foundations caused the ceiling and wall in one of the top-level rooms to begin to crack and showed early signs of separation.

Proposed Solution

The engineering team recommended using injectable polyurethane grout. AP Lift 430 was selected for the job because of its high expansion of 22x and compressive strength of 7,200 psf. This polymer is also hydrophobic, which prevents water from causing further erosion of the void.

Implementation

  1. Rod Placement: Injection rods were inserted horizontally into the void’s back, spaced 4 feet apart.
  2. Foam Injection: Foam was injected through the rods until emerging from the exposed void area. This step ensured that the foam reached the farthest areas of the cavity.
  3. Free-Shooting: The remaining exposed void was filled by direct foam application, ensuring comprehensive coverage.

Results and Conclusion

The end result was 658 gallons of expanded AP Lift 430 injected underneath the void. The polyurethane injection, combined with regrading work done in collaboration with a local engineering firm, successfully solved the issue and prevented further void formation underneath the student housing.

Want more information on geotechnical polymers and equipment?

Download the Info-Packed Geotech Product Catalog!

Topics: All Posts, Fill Voids

Case Study - Sealing a Telecom Data Center Water Leak

Posted by Landon Feese on Jul 30, 2024 10:00:00 AM

Banner - Sealing a Telecom Data Center Water Leak

Body - Sealing a Telecom Data Center Water LeakA broadband provider in Alpharetta, Georgia, contacted a local leak seal contractor after discovering water infiltration through a crawl space wall during heavy rainstorms. Over time, cracks had developed, allowing not only water but also sediment to enter, creating substantial voids outside the fissures upon inspection. Given the sensitivity and high value of the equipment housed within the facility, eliminating all potential leaks in the crawl space became a top priority.

Powerful Polymers

The technicians chose Alchatek’s Spetec PUR HighFoamer to address this leak. This highly expansive polyurethane grout creates a robust, waterproof barrier, effectively sealing a wide variety of leaks without extensive excavation. Spetec PUR HighFoamer’s remarkable expansion capacity (40x-50x) ensures comprehensive coverage and a tight seal, making it ideal for projects requiring minimal downtime. Its NSF 61 certification guarantees safety for potable water applications, positioning this product as a versatile and cost-effective choice for leak sealing projects across various industries.

Painless Procedures

The repair process consisted of three efficient steps. First, the crew drilled through the concrete wall, installing zerk fittings into each hole for subsequent injections. Next, they used an electric airless sprayer to inject water into each fitting, ensuring proper activation of the foam. Finally, they injected Spetec PUR HighFoamer through these fittings. This created a curtain wall of polyurethane foam that effectively sealed the cracks, prevented further water ingress, and filled voids in the soil substrate.

Rapid Results

Within 24 hours, the technicians successfully sealed all leaks in the underlying crawl space. This injection process was completed in a fraction of the time required for a full membrane replacement. Months after the repair, following several heavy rainstorms, the facility manager confirmed that the crawl space has remained completely dry, with no recurrence of leaks.

Want more information about sealing leaks with polyurethane?

Download an Info-Packed Infrastructure Leak Seal and Void Fill Brochure!

Topics: All Posts, Seal Leaks