
A Tennessee state correctional facility had a significant infrastructure failure when newly installed plumbing beneath a concrete slab malfunctioned. In an attempt to address the issue, the original contractor backfilled the entire plumbing system with concrete. When this approach proved unsuccessful, a second contractor was brought in to demolish the concrete and properly repair the plumbing systems. This process left a substantial void beneath the slab that required immediate filling to restore structural integrity and minimize facility downtime.
Initial Assessment
Following the plumbing repairs, engineers assessed a void measuring approximately 200 square feet in area and 4-5 feet in depth, totaling roughly 800-1,000 cubic feet of empty space beneath the concrete slab. The prison's security restrictions severely limited access to equipment, making traditional concrete replacement a challenging and time-consuming process. The facility required a solution that would minimize disruption to operations while providing structural support equivalent to the original concrete base.
Proposed Solution
Working with Alchatek, Mid-South Concrete Lifting recommended using AP Fill 420, a two-component structural polyurethane foam, to fill the substantial void. This approach offered several critical advantages for the correctional facility environment. The material could be applied through a simple hose system, eliminating the need for heavy concrete trucks and mixing equipment that would be difficult to maneuver through security checkpoints. The foam's rapid curing time would significantly reduce the project timeline, and its structural properties would provide adequate load-bearing capacity for the slab above.
Procedures
- Security clearance and equipment inspection were completed to bring polyurethane application equipment into the facility.
- The void was accessed through existing openings created during the concrete removal process.
- AP Fill 420 was applied using a free-shooting technique.
- Material application was monitored to ensure complete filling and proper expansion throughout the space.
Results
The void filling was completed in 3 hours versus an estimated week for concrete replacement. AP Fill 420 polyurethane foam successfully filled the entire void space and provided adequate structural support. Prison officials expressed satisfaction with the efficiency and minimal operational disruption, leading the contractor to look at another similar project at a different state facility.
The polyurethane approach delivered 65-75% cost savings compared to traditional concrete replacement when accounting for materials, equipment, labor, and reduced facility disruption. The accelerated timeline also eliminated the extended security coordination costs typically associated with longer construction projects.



Alchatek has streamlined its two-component production system according to 

Fifteen, two‑unit condominium buildings exhibited differential settlement and interior slab movement from loose organics and voiding, risking structural performance and livability. Continuous occupancy required a rapid, low‑disruption remediation strategy that delivered durable lift and stabilization. The job was completed by foundation repair specialists at 

In the fast-paced world of geotechnical contracting, having a team member who truly understands the grind of the field can make all the difference. That's why we're thrilled to introduce Antwon Butts, our newest Tech Support Technician on the Technical Services team. With a career built on the front lines, Antwon steps into this role ready to bridge the gap between product innovation and real-world application, helping contractors like you tackle everything from soil stabilization to complex grouting challenges with confidence.
A south Georgia roadway developed a sinkhole over a double 48-inch RCP storm line about 10 feet deep, threatening lane safety and mobility. Replacement costs were prohibitive and would require extended closure and excavation.
A fire station access roadway developed cracking from subsurface voids caused by storm drain seam gaps that washed out soil during heavy rain, threatening daily emergency operations and pavement integrity. Geotech specialists from 
Attention Geotech Professionals!
A multi-level parking facility in downtown Los Angeles was experiencing significant water infiltration through its concrete ceiling. Building management had noticed increasing water staining and active leakage, particularly following rain events. The water migration around electrical conduits and light fixtures was most concerning, creating potential safety hazards with the electrical systems. Previous attempts to seal the ceiling using conventional surface treatments had failed to resolve the issue. With the structure serving high-end retail clients, the property management company required a solution to effectively stop the leaks while minimizing disruption to the facility's daily operations.
The property manager for a multi-level parking garage contacted 
MixMaster Gun Cleaner 160 is the latest innovation designed to streamline maintenance for contractors using the 