
After the removal of a wooden deck, dangerous voids under the brick pavers were revealed in a luxury apartment pool deck, threatening its integrity and safety. The property owner contacted Helicon, a trusted foundation repair company.
Initial Assessment
Subsurface investigation confirmed extensive voiding with no practical access for excavation during occupancy. Demolition/replacement would take weeks, cost tens of thousands, and the pool would need to be closed during peak season.
Proposed Solution
The contractor selected AP Lift 440 for its hydro‑insensitivity, ~15‑minute cure, and ~80 psi compressive strength. This material was ideal for increasing the soil's bearing capacity and restoring the pool to its correct state.
Procedures
- Map the void locations using ground-penetrating radar and probing.
- Establish an injection grid targeting the largest voids first.
- Drill strategic injection ports through pavers to void spaces.
- Inject AP Lift 440 to refusal using calibrated pressure monitoring.
- Allow 15-minute cure
- Seal injection ports and restore surface aesthetics.
Results
- Structural integrity fully restored with 1,200 lbs of AP Lift 440, filling all voids.
- Zero operational downtime; pool deck remained accessible throughout repair.
- Approximately 70-90% cost savings compared to demolition/replacement alternatives.



A Tennessee state correctional facility had a significant infrastructure failure when newly installed plumbing beneath a concrete slab malfunctioned. In an attempt to address the issue, the original contractor backfilled the entire plumbing system with concrete. When this approach proved unsuccessful, a second contractor was brought in to demolish the concrete and properly repair the plumbing systems. This process left a substantial void beneath the slab that required immediate filling to restore structural integrity and minimize facility downtime.
A fire station access roadway developed cracking from subsurface voids caused by storm drain seam gaps that washed out soil during heavy rain, threatening daily emergency operations and pavement integrity. Geotech specialists from 
A property in Atlanta featured a multi-level parking structure with a split-level design. The upper-level parking area began showing signs of significant distress, with visible cracking and pavement deterioration. Investigation revealed that soil was actively migrating through a lower retaining wall of the parking structure, creating voids behind the wall and compromising support for the pavement above. The color change in the asphalt surface clearly marked the affected area, and the problem was getting progressively worse, posing both functional and safety concerns for vehicles using the facility.
The 
A Utah-based geotech specialist partnered with a general contractor to address a critical DOT infrastructure challenge involving the replacement of an existing culvert on a major roadway in Utah. The project involved the installation of precast concrete slabs on both sides of the box culvert, designed to create a seamless transition from the culvert to the compacted road base.


Suburban Basement
An old farmhouse with a wrap-around porch in Lake Orion, Michigan, presented a unique challenge. Beneath the porch lay an old cellar, initially used for coal storage but now serving only as a conduit for a well line into the residence. The primary concern was the inward buckling of the cellar walls, which posed a significant safety hazard. Many contractors suggested demolishing the porch and excavating the cellar, a solution that would have incurred substantial costs for both demolition and reconstruction.
The owner of a gas manufacturing facility contacted a Georgia-based contractor regarding significant floor settlement issues, with a warehouse slab dropping approximately 3-4 inches. The settlement made issues for the forklift traversing in and out of the warehouse and posed a risk to the workers.


Essential Details
