
A critical downtown Houston pedestrian tunnel had persistent water infiltration affecting the ceiling, walls, and floor throughout the structure. The tunnel serves as vital underground infrastructure in Houston's urban core, where any significant disruption would impact pedestrian traffic and building access. Initial observations revealed widespread moisture intrusion, but the full extent of the problem remained unclear until interior finishes could be removed for proper assessment. The facility required a rapid, effective solution that would minimize downtime and restore the tunnel's watertight integrity.
Initial Assessment
Once sheetrock was removed from affected areas, engineers discovered extensive water infiltration through multiple pathways in the concrete structure. Moisture intrusion was occurring through joints, cracks, and penetrations, creating a complex leak pattern that compromised the tunnel's structural integrity and usability. Traditional repair methods would have required extensive excavation from above or complete tunnel closure for membrane installation - both prohibitively disruptive options in Houston's dense downtown corridor. The assessment revealed that targeted injection could address the root cause of infiltration without major structural modifications.
Proposed Solution
Alchatek recommended using Spetec PUR GT350, a hydrophilic polyurethane grout specifically designed for active leak sealing in underground structures. This single-component material was selected for its ability to react with water to form an expanding, flexible foam that creates a permanent, waterproof barrier. The injection approach would allow precise targeting of leak sources while maintaining tunnel accessibility throughout the repair process. The polyurethane's expansion properties would ensure complete void filling and crack sealing, even in areas with irregular geometries or active water flow.
Procedures
- Mapped all visible leak points and moisture intrusion areas throughout the tunnel structure.
- Drilled strategic injection ports at locations determined to intercept water infiltration pathways.
- Injected polyurethane grout through ports using positive displacement pumps, monitoring for material refusal and leak cessation.
- Conducted systematic injections across all identified problem areas, adjusting techniques based on local conditions.
- Verified complete sealing through visual inspection and moisture monitoring following cure completion.
Results
The polyurethane injection process successfully eliminated water infiltration throughout the tunnel structure, restoring its watertight integrity without requiring facility closure or major structural modifications. Post-treatment inspections confirmed the complete cessation of leaks, with the tunnel remaining dry even during subsequent heavy rain events. The minimally invasive approach allowed the tunnel to remain operational throughout the repair process, avoiding costly service interruptions. For a typical tunnel section, this represents over 95% cost savings compared to traditional methods. Additionally, avoiding tunnel closure prevented an estimated $10,000 to $ 25,000 in daily economic losses due to disrupted pedestrian traffic and building access, further amplifying the financial benefits of this innovative approach.



A tunnel structure in the Mobile, Alabama area had persistent water infiltration at the interface between concrete and metal components. The leak was traced to a tight crack at the joint, allowing water to migrate into the tunnel and cause visible staining, as well as potential long-term deterioration. The client sought a solution that would seal the leak without requiring major demolition or extended tunnel closure.
After the removal of a wooden deck, dangerous voids under the brick pavers were revealed in a luxury apartment pool deck, threatening its integrity and safety. The property owner contacted 

A Tennessee state correctional facility had a significant infrastructure failure when newly installed plumbing beneath a concrete slab malfunctioned. In an attempt to address the issue, the original contractor backfilled the entire plumbing system with concrete. When this approach proved unsuccessful, a second contractor was brought in to demolish the concrete and properly repair the plumbing systems. This process left a substantial void beneath the slab that required immediate filling to restore structural integrity and minimize facility downtime.
Fifteen, two‑unit condominium buildings exhibited differential settlement and interior slab movement from loose organics and voiding, risking structural performance and livability. Continuous occupancy required a rapid, low‑disruption remediation strategy that delivered durable lift and stabilization. The job was completed by foundation repair specialists at 

A south Georgia roadway developed a sinkhole over a double 48-inch RCP storm line about 10 feet deep, threatening lane safety and mobility. Replacement costs were prohibitive and would require extended closure and excavation.
A fire station access roadway developed cracking from subsurface voids caused by storm drain seam gaps that washed out soil during heavy rain, threatening daily emergency operations and pavement integrity. Geotech specialists from 
A multi-level parking facility in downtown Los Angeles was experiencing significant water infiltration through its concrete ceiling. Building management had noticed increasing water staining and active leakage, particularly following rain events. The water migration around electrical conduits and light fixtures was most concerning, creating potential safety hazards with the electrical systems. Previous attempts to seal the ceiling using conventional surface treatments had failed to resolve the issue. With the structure serving high-end retail clients, the property management company required a solution to effectively stop the leaks while minimizing disruption to the facility's daily operations.

The property manager for a multi-level parking garage contacted 
One Atlanta Plaza experienced significant settling of sidewalks and approach slabs around the perimeter of the building, creating safety hazards for pedestrians and visitors. The multi-story structure includes underground parking levels supported by piles, which remained stable, but the transition areas connecting to surrounding sidewalks were built on compacted fill. Over time, differential settlement occurred between the pile-supported structure and the soil-supported approach slabs, with some areas dropping approximately half an inch. Building management had previously attempted fixes by creating concrete "ramps" at transition points, but these temporary solutions continued to deteriorate as settlement progressed.