
A Tennessee state correctional facility had a significant infrastructure failure when newly installed plumbing beneath a concrete slab malfunctioned. In an attempt to address the issue, the original contractor backfilled the entire plumbing system with concrete. When this approach proved unsuccessful, a second contractor was brought in to demolish the concrete and properly repair the plumbing systems. This process left a substantial void beneath the slab that required immediate filling to restore structural integrity and minimize facility downtime.
Initial Assessment
Following the plumbing repairs, engineers assessed a void measuring approximately 200 square feet in area and 4-5 feet in depth, totaling roughly 800-1,000 cubic feet of empty space beneath the concrete slab. The prison's security restrictions severely limited access to equipment, making traditional concrete replacement a challenging and time-consuming process. The facility required a solution that would minimize disruption to operations while providing structural support equivalent to the original concrete base.
Proposed Solution
Working with Alchatek, Mid-South Concrete Lifting recommended using AP Fill 420, a two-component structural polyurethane foam, to fill the substantial void. This approach offered several critical advantages for the correctional facility environment. The material could be applied through a simple hose system, eliminating the need for heavy concrete trucks and mixing equipment that would be difficult to maneuver through security checkpoints. The foam's rapid curing time would significantly reduce the project timeline, and its structural properties would provide adequate load-bearing capacity for the slab above.
Procedures
- Security clearance and equipment inspection were completed to bring polyurethane application equipment into the facility.
- The void was accessed through existing openings created during the concrete removal process.
- AP Fill 420 was applied using a free-shooting technique.
- Material application was monitored to ensure complete filling and proper expansion throughout the space.
Results
The void filling was completed in 3 hours versus an estimated week for concrete replacement. AP Fill 420 polyurethane foam successfully filled the entire void space and provided adequate structural support. Prison officials expressed satisfaction with the efficiency and minimal operational disruption, leading the contractor to look at another similar project at a different state facility.
The polyurethane approach delivered 65-75% cost savings compared to traditional concrete replacement when accounting for materials, equipment, labor, and reduced facility disruption. The accelerated timeline also eliminated the extended security coordination costs typically associated with longer construction projects.



A fire station access roadway developed cracking from subsurface voids caused by storm drain seam gaps that washed out soil during heavy rain, threatening daily emergency operations and pavement integrity. Geotech specialists from 
A property in Atlanta featured a multi-level parking structure with a split-level design. The upper-level parking area began showing signs of significant distress, with visible cracking and pavement deterioration. Investigation revealed that soil was actively migrating through a lower retaining wall of the parking structure, creating voids behind the wall and compromising support for the pavement above. The color change in the asphalt surface clearly marked the affected area, and the problem was getting progressively worse, posing both functional and safety concerns for vehicles using the facility.
The 
A Utah-based geotech specialist partnered with a general contractor to address a critical DOT infrastructure challenge involving the replacement of an existing culvert on a major roadway in Utah. The project involved the installation of precast concrete slabs on both sides of the box culvert, designed to create a seamless transition from the culvert to the compacted road base.


Suburban Basement
An old farmhouse with a wrap-around porch in Lake Orion, Michigan, presented a unique challenge. Beneath the porch lay an old cellar, initially used for coal storage but now serving only as a conduit for a well line into the residence. The primary concern was the inward buckling of the cellar walls, which posed a significant safety hazard. Many contractors suggested demolishing the porch and excavating the cellar, a solution that would have incurred substantial costs for both demolition and reconstruction.
The owner of a gas manufacturing facility contacted a Georgia-based contractor regarding significant floor settlement issues, with a warehouse slab dropping approximately 3-4 inches. The settlement made issues for the forklift traversing in and out of the warehouse and posed a risk to the workers.


Essential Details
