
An Atlanta contractor contacted Alchatek for assistance with a void filling job in the parking garage at Brookhaven City Hall. The bottom floor of the garage exhibited significant voids beneath the concrete slab, posing risks of settlement and structural instability.
Initial Assessment
An Alchatek support technician worked with the contractor to conduct a thorough assessment and implemented a targeted void-filling solution to restore stability.
Proposed Solution
Alchatek recommended using AP Lift 430 Fast, a high-performance polyurethane foam designed for rapid void filling and stabilization. This material was selected for its quick-setting properties, high compressive strength, and ability to effectively fill voids while providing robust support for the concrete slab. The approach ensured minimal disruption to the parking garage operations, as it required no extensive excavation.
Procedures
- Established a grid pattern to guide the placement of injection points on the bottom floor of the parking garage.
- Drilled holes through the concrete slab at strategically determined injection points to access the voids beneath.
- Injected AP Lift 430 Fast polyurethane foam into the drilled holes, ensuring comprehensive void coverage from bottom to top.
- Patched drilled holes to restore the surface integrity of the concrete slab.
Results
The void-filling project at the Brookhaven City Hall parking garage was a success. The application of AP Lift 430 Fast effectively filled all identified voids, eliminating the risk of further settlement. The stabilized concrete slab restored the structural integrity of the garage floor, ensuring a safe and functional environment for vehicles and pedestrians. The solution minimized operational downtime and avoided costly excavation, preserving the facility’s functionality.



After the removal of a wooden deck, dangerous voids under the brick pavers were revealed in a luxury apartment pool deck, threatening its integrity and safety. The property owner contacted 
A Tennessee state correctional facility had a significant infrastructure failure when newly installed plumbing beneath a concrete slab malfunctioned. In an attempt to address the issue, the original contractor backfilled the entire plumbing system with concrete. When this approach proved unsuccessful, a second contractor was brought in to demolish the concrete and properly repair the plumbing systems. This process left a substantial void beneath the slab that required immediate filling to restore structural integrity and minimize facility downtime.
A fire station access roadway developed cracking from subsurface voids caused by storm drain seam gaps that washed out soil during heavy rain, threatening daily emergency operations and pavement integrity. Geotech specialists from 
A property in Atlanta featured a multi-level parking structure with a split-level design. The upper-level parking area began showing signs of significant distress, with visible cracking and pavement deterioration. Investigation revealed that soil was actively migrating through a lower retaining wall of the parking structure, creating voids behind the wall and compromising support for the pavement above. The color change in the asphalt surface clearly marked the affected area, and the problem was getting progressively worse, posing both functional and safety concerns for vehicles using the facility.
The 
A Utah-based geotech specialist partnered with a general contractor to address a critical DOT infrastructure challenge involving the replacement of an existing culvert on a major roadway in Utah. The project involved the installation of precast concrete slabs on both sides of the box culvert, designed to create a seamless transition from the culvert to the compacted road base.


Suburban Basement
An old farmhouse with a wrap-around porch in Lake Orion, Michigan, presented a unique challenge. Beneath the porch lay an old cellar, initially used for coal storage but now serving only as a conduit for a well line into the residence. The primary concern was the inward buckling of the cellar walls, which posed a significant safety hazard. Many contractors suggested demolishing the porch and excavating the cellar, a solution that would have incurred substantial costs for both demolition and reconstruction.
The owner of a gas manufacturing facility contacted a Georgia-based contractor regarding significant floor settlement issues, with a warehouse slab dropping approximately 3-4 inches. The settlement made issues for the forklift traversing in and out of the warehouse and posed a risk to the workers.

