Alchatek Infrastructure Repair Blog: Polyurethane Leak Seal Injection, Soil Stabilization, Concrete Leveling

Case Study - Tennessee State Prison: Rapid Void Filling Solution

Written by Landon Feese | Nov 5, 2025 3:00:03 PM

A Tennessee state correctional facility had a significant infrastructure failure when newly installed plumbing beneath a concrete slab malfunctioned. In an attempt to address the issue, the original contractor backfilled the entire plumbing system with concrete. When this approach proved unsuccessful, a second contractor was brought in to demolish the concrete and properly repair the plumbing systems. This process left a substantial void beneath the slab that required immediate filling to restore structural integrity and minimize facility downtime.

Initial Assessment

Following the plumbing repairs, engineers assessed a void measuring approximately 200 square feet in area and 4-5 feet in depth, totaling roughly 800-1,000 cubic feet of empty space beneath the concrete slab. The prison's security restrictions severely limited access to equipment, making traditional concrete replacement a challenging and time-consuming process. The facility required a solution that would minimize disruption to operations while providing structural support equivalent to the original concrete base.

Proposed Solution

Working with Alchatek, Mid-South Concrete Lifting recommended using  AP Fill 420, a two-component structural polyurethane foam, to fill the substantial void. This approach offered several critical advantages for the correctional facility environment. The material could be applied through a simple hose system, eliminating the need for heavy concrete trucks and mixing equipment that would be difficult to maneuver through security checkpoints. The foam's rapid curing time would significantly reduce the project timeline, and its structural properties would provide adequate load-bearing capacity for the slab above.

Procedures

  1. Security clearance and equipment inspection were completed to bring polyurethane application equipment into the facility.
  2. The void was accessed through existing openings created during the concrete removal process.
  3. AP Fill 420 was applied using a free-shooting technique.
  4. Material application was monitored to ensure complete filling and proper expansion throughout the space.

Results

The void filling was completed in 3 hours versus an estimated week for concrete replacement. AP Fill 420 polyurethane foam successfully filled the entire void space and provided adequate structural support. Prison officials expressed satisfaction with the efficiency and minimal operational disruption, leading the contractor to look at another similar project at a different state facility.

The polyurethane approach delivered 65-75% cost savings compared to traditional concrete replacement when accounting for materials, equipment, labor, and reduced facility disruption. The accelerated timeline also eliminated the extended security coordination costs typically associated with longer construction projects.

Want more information on geotech products and equipment?