Alchatek Infrastructure Repair Blog: Polyurethane Leak Seal Injection, Soil Stabilization, Concrete Leveling

Case Study - Sealing Parking Structure Elevator Pit Leaks

Written by Landon Feese | Sep 24, 2025 2:00:00 PM

The property manager for a multi-level parking garage contacted Pavecon regarding persistent water infiltration in an elevator pit. The facility engaged Allana Buick & Bers, Inc. to develop a remediation strategy. Water leakage in elevator pits poses risks to equipment, safety, and can lead to service disruptions.

Initial Assessment

Inspection revealed multiple water entry points in the concrete walls of the elevator pit. The recurring water infiltration threatened the elevator system's integrity and created potential safety issues. Traditional repair methods would require extensive excavation and significantly disrupt parking facility operations, making them impractical and costly. The assessment determined that an effective solution was needed to address active leaks and provide long-term waterproofing without frequent maintenance.

Proposed Solution

The team selected a specialized polyurethane injection system (Spetec PUR F400) for the elevator pit leakage. This product effectively seals active water leaks in concrete structures by creating a waterproof barrier without extensive excavation. The method required only brief elevator shutdown periods rather than extended facility closures and could be applied even with active water infiltration.

Procedures

  1. Thoroughly cleaned repair areas to remove dirt, debris, and loose concrete that could compromise adhesion.
  2. Drilled through the concrete wall at strategic locations to access water infiltration pathways.
  3. Installed injection ports (zerk fittings) into each drilled hole to facilitate polymer application.
  4. Injected water when necessary to properly activate the polyurethane foam reaction.
  5. Polyurethane injection material was applied through installed ports, allowing it to expand and fill voids.
  6. Performed sequential injection following a pattern to ensure complete coverage of affected areas.
  7. Removed injection ports and patched drill holes with hydraulic cement after the injection process.
  8. Performed final inspection to verify cessation of all leaks.

Results

The polyurethane injection process successfully sealed all water infiltration points in the elevator pit, creating a waterproof barrier. The repair was completed within the scheduled timeframe, minimizing elevator system downtime. The project addressed approximately 17 linear feet of repair work.

After several substantial rain events, the elevator pit remained completely dry, confirming the solution's effectiveness. The property manager expressed satisfaction with the results, subsequently requesting additional services at other facilities and providing positive recommendations.

This solution demonstrated significant cost advantages over traditional methods, saving an estimated 60-70% compared to conventional waterproofing approaches while preventing potential damage to electrical and mechanical components.

Want more information on leak seal material and equipment?