Alchatek Infrastructure Repair Blog: Polyurethane Leak Seal Injection, Soil Stabilization, Concrete Leveling

Case Study - DOT Culvert Void Fill

Written by Landon Feese | May 7, 2025 2:00:00 PM

A Utah-based geotech specialist partnered with a general contractor to address a critical DOT infrastructure challenge involving the replacement of an existing culvert on a major roadway in Utah. The project involved the installation of precast concrete slabs on both sides of the box culvert, designed to create a seamless transition from the culvert to the compacted road base.

Site Investigation and Challenge

During the design phase, engineers identified that constructing a compacted road base beneath the slab would inevitably leave voids underneath. These voids posed a risk of uneven support and potential rocking of the slab when subjected to heavy traffic load.

Proposed Solution

To address this, ¾” holes were drilled four feet apart to allow for injection rods to be inserted through the slab. The foam selected for this slab was AP Lift 440 structural foam due to its rapid expansion and high strength needed for DOT projects. This foam expands 17-19 times its original volume within 8-10 seconds of injection, ensuring comprehensive void filling. Dial indicators were used to ensure that there was no vertical movement of the slab during the injection process.  

Results and Conclusion

The entire operation was executed in approximately three hours, utilizing about 400 lbs of structural foam. This successful application filled all of the voids, providing uniform support for the precast slabs and enhancing overall road stability. The rapid curing properties of the foam allowed for swift project completion with minimal disruption to traffic.

Want more information on stabilizing soil with polyurethane?