The primary issue was leaking grout plugs, which were 2-inch diameter, straight-threaded plugs welded into place after the initial grouting process. These plugs exhibited varying degrees of water seepage, with flow rates estimated at a few gallons per minute. The leaks were attributed to anticipated movement between the steel pipe and the surrounding rock due to temperature changes and vibrations. Based on these conditions, a flexible chemical grout was determined to be the best solution to seal the leaks while accommodating future movement.
Alchatek recommended injecting Spetec PUR F400, a flexible polyurethane grout, to seal the leaks. This grout was selected because of its ability to bond effectively while maintaining flexibility to withstand differential movement between the steel pipe and surrounding materials. The plan involved drilling into the existing grout plugs and injecting Spetec PUR F400 through packers to confine the grout and ensure a complete seal. The project utilized packers for controlled injection and a Titan Impact 440 pump to deliver the grout. Alchatek Gen Cat was used to manage the grout’s reaction time based on the specific site conditions.
1. Preparation:
2. Injection Process:
3. Post-Repair Monitoring:
The initial injection process sealed most of the identified leaking grout ports, effectively stopping water infiltration at those locations. However, water subsequently found new paths, resulting in additional leaks from previously sealed ports. The team used the same materials and procedures to address these additional leaks through follow-up injections. Ultimately, all leaks were successfully sealed, restoring the integrity of the steel pipe installation.