the pool was still failing.
Penetrometer testing confirmed the loss. The cone advanced through the upper 2.6 feet without a recorded blow, and resistance stayed in single digits down to 3.6 feet. Below that, the profile firmed into competent sandy clay, reaching refusal at 9.5 feet. The design remedy called for scraping back two feet of subgrade and rebuilding it, a three week job.
The contractor specified AP Lift 475 with the Deep Lock® process. The two-component polyurethane expands into weak soil and compacts it in place. Crews injected through rods driven from the surface, leaving the shell and deck undisturbed.
Logged baseline penetrometer readings to refusal
Laid out a 4-foot injection grid across 10,000 sq. ft. around the pool
Drove 900 injection rods and injected AP Lift 475
Injected a second level beneath the shell, compacting the soil between
Re-tested the profile against baseline
Restored bearing in the eroded upper three feet, where cumulative blow counts rose from 2 to 101
Increased cumulative resistance 139% through the upper 6.6 feet, with values below that depth unchanged
Stabilized 10,000 sq ft to a treated depth of 10ft
Eliminated the two-foot scrape and rebuild
Completed in two days against the three-week estimate